Licence conditions for pollution studies and reduction program


  

Licence conditions for pollution studies and reduction programs

Summary
 
Licence number: 1688
Title: PRP 306: Separation of the Woolloomooloo combined sewer and stormwater system
Start date: 06 Jul 2016
 
Licence Condition
306.1 By 31 December 2019 the licensee must undertake all works and actions necessary to completely separate the sewer and stormwater system in Sydney East SCAMP (Woolloomooloo).
306.2 The sewerage system constructed to comply with 306.1 is to meet a discharge frequency target of 20 overflow events in 10 years.
306.3 The licensee must submit to the EPA for approval, a draft water quality monitoring plan for the project, with a monitoring objective of assessing the water quality benefits from the works required under 306.1. The monitoring program in the plan is to include appropriate baseline monitoring to be completed prior to the works under 306.1 commencing and post-construction monitoring. The plan is to be submitted to the EPA by 30 September 2016.
306.4 The licensee must implement the plan approved by the EPA under 306.3. The licensee must provide an interim monitoring report to the EPA by 1 October 2017 which contains the results of the baseline monitoring. A final monitoring report is to be provided to the EPA by 1 April 2021.
306.5 In addition to the reporting requirements of condition R5.6, the licensee must submit with each Annual System Performance Report: i)  details of any investigations, plans, works and activities that were undertaken during the reporting period and an outline of progress toward achieving the objectives of this PRP.