Non-Compliance detail


  
Summary
 
Licence number: 563
Annual Return Start: 20 Jul 2008
Annual Return End: 19 Jul 2009
Date Received: 17 Sep 2009
 
Licence Condition numberType of non-complianceEPA actionsNo. of times occurred
M2 DEPOSITIONAL DUST GAUGE C1 WAS NOT SAMPLED ON THE DECEMBER 2008 SAMPLE EVENT DUE TO BROKEN GAUGE Appropriate Action taken by licensee 1
M2.1 TOTAL SUSPENDED PARTICLES HVS1 WAS NOT SAMPLED ON ONE SCHEDULED OCCASION Appropriate Action taken by licensee 1
O1.1 DISCHARGE OF WATEROUTSIDE LICENCE CONDITION C3 DAM OVERFLOWED (0.4ML) OF NINE MILE CREEK OVER A 12 HOUR PERIOD ON THE 15 FEBRUARY 2009 104MM OF RAINFALL OVER 2 DAYS EPA has written to licensee regarding non-compliance and relevant action 1
L7 EXCEEDANCE OF THE MAXIMUM OVERPRESSURE LIMIT OF 120DBL FOR EPL563 AT A SINGLE COMMUNITY MONITORING LOCATION WITHOUT A PRIVATE AGREEMENT. BLAST MONITORING REGISTERED AN OVERPRESSURE LEVEL OF 123DBL EPA has written to licensee regarding non-compliance and relevant action 1