Non-Compliance detail


  
Summary
 
Licence number: 4022
Annual Return Start: 01 Jan 2015
Annual Return End: 31 Dec 2015
Date Received: 29 Feb 2016
 
Licence Condition numberType of non-complianceEPA actionsNo. of times occurred
Schedule 4A, D17 Due to GIS/GPS operational map discrepancy - first order filter strip partially harvested (2 trees removed). Area seeded and mulched. Protocol developed to ensure that machine operators are using the latest harvest plan operation map. EPA to monitor future compliance with this condition 1