Non-Compliance detail


  
Summary
 
Licence number: 13007
Annual Return Start: 01 Jan 2021
Annual Return End: 31 Dec 2021
Date Received: 12 Aug 2022
 
Licence Condition numberType of non-complianceEPA actionsNo. of times occurred
L3.1 Increasing concentration of salts detected in groundwater in monitoring bore MPGM5_D5. Bore D5 is monitored on a quarterly basis as part of the leak detection system for the adjacent double-lined brine wastewater pond A. EPA action determined as part of scheduled inspection program 1
L3.8 Water exceeding limits for turbidity and total suspended solids in Condition L3.8 of the EPL was discharged at LDP12. EPA action determined as part of scheduled inspection program 1
L3.2 Solid particle concentration for monitoring point 3 on 20 May 2021 was 120 mg/m3, exceeding the 50 mg/m3 licence limit. EPA action determined as part of scheduled inspection program 1
M2.2 Monitoring data for Sulfur Dioxide, Nitrogen Oxide, Oxygen and Moisture were not recorded on a continuous basis on Unit 1 over a 5 day period as required by EPL13007 due to a computer malfunction. EPA action determined as part of scheduled inspection program 1
L3.1 Release of fresh water fromm Fish River water pipeline, resulting in localised erosion and drainage into stormwater drain and ultimately the final holding pond. EPA action determined as part of scheduled inspection program 1